King's Cross Station

Regeneration projects within one of London's busiest rail terminals.

  • Client

    Network Rail

  • Contractor

    Taylor Woodrow
    J Murphy

  • Architect

    John McAslan and Partners,
    Stanton Williams

  • Completion Date

    2014 – 2016

  • Scope of works

    Package 3: Platform level scenic lift, scenic stair, over track passenger bridges, walkways & balustrading.

    Package 6: Main concourse blast resistant balustrading, glass wall Linings, staircases, shopfronts and bulkheads.

    Package 7: Bomb Blast resistant canopy to the main station entrance and bomb blast resistant shopfront to the retail kiosk.

Over track, platform works and significant remodelling of the stations internal and external concourses during engineering hours. Each package of works presented its own significant challenge, whilst maintaining pedestrian access to, and operation of one of London’s busiest transport hubs.